Alpine Pipeline River Crossing 2010 Monitoring Report

Originally constructed during the winter of 1998/1999, the Alpine Pipeline System crosses three major rivers between the Alpine Development CD1 facility and the tie-in to the Kuparuk Pipeline. The three river crossings are the aboveground crossings of the Kachemach River and the Miluveach River; and the horizontal directionally drilled (HDD) crossing of the East Channel of the Colville River. In 2001, initial monitoring of the HDD crossing was conducted (Baker 2002). Annual monitoring of the HDD, Kachemach River, and the Miluveach River crossings was conducted from 2003 through 2006 (Baker 2003, 2004, 2005, 2006). Over the course of these five years of monitoring, no significant scour, erosion, or VSM (vertical support member) tilt were observed at the Kachemach and Miluveach River crossings. As a result, in the fall of 2006, a five-year monitoring interval was recommended. In 2007, monitoring was therefore limited to the HDD crossing (Baker 2007). The 2008 monitoring was conducted at all three crossing locations (Baker 2008) and included surveying by Kuukpik/LCMF, LLC (LCMF). In both 2009 and 2010, LCMF surveying was conducted only at the HDD crossing location. Baker conducted visual observations and tilt measurements at all three crossing locations. It is anticipated that LCMF will continue to provide annual bank erosion survey data for the HDD crossing, and that bank erosion surveying of the Kachemach and Miluveach will occur again in 2013. Monitoring allows for a historic comparison between observed conditions and the design criteria, as required by the Right-of-Way Lease/Grant Stipulations and the Alpine Surveillance and Monitoring Program. Monitoring is conducted to document the condition of the pipelines and channel morphology at each of the river crossings. The primary objective is documentation

Datos y Recursos

Información Adicional

Campo Valor
Última actualización 17 Diciembre, 2019, 10:16 (AKST)
Creado 17 Diciembre, 2019, 10:16 (AKST)
Estado Complete
Start Date 2010-04-01
End Date 2010-10-30
Other Agencies ConocoPhillips